Manufacturing
Maersk
San Antonio, Valparaíso Region
2012-2013
Environmental Impact Statement, basic and detailed engineering, management of procurement of equipment and materials, construction management and technical inspection of works.
The project for Maersk Container Industry was executed under the EPCM modality and consisted in the erection of a refrigerated container factory. The construction of the plant was approximately 70,000 m2 and was built on a plot of 330,000 m2, producing 40,000 containers per year.