With proven experience, at Pares&Alvarez we have the methodology and professionals capable of leading the development process of a project, both greenfield and brownfield. We cover project management in all its stages, from engineering control, procurement, construction contract bidding, construction management and start-up.
This project makes northern Chile independent of the supply of liquefied gas, reduced vehicle traffic and contributes to the development and independence of the area.
The proposal focused on the enhancement of the Flash Furnace, to bring the capacity from 825 ktpa to 1,170 ktpa, for Codelco's Chuquicamata foundry.
The project considered the basic and detailed engineering, supplies, construction of civil works, manufacture and assembly of metal structures type geodesic dome to realize the coverage of the coal yard, which covered an area of 45,000 m2.
The EPC was developed for two storage silos (750 ton) and compact lime milk preparation systems (8.6 ton/h).
The project for Maersk Container Industry was executed under the EPCM modality.
The project included the installation of two laminate lines for the production of melamine boards and an impregnation line for the preparation of the melamine papers required for the board laminate process.
Expansion of the glass packaging production plant and also considered the installation of a new furnace and three packaging production lines. For this, the existing industrial warehouse was expanded by 14,000 m2.
As the detailed engineering began to progress, advances were made in the management of equipment purchases in order to begin construction, all under strict control of compliance with deadlines and CAPEX.
Construction of a new iron ore collection plant and installation of new recovery and transport belts for CAP Minería.
Pares&Alvarez supported the discipline engineers of the Huasco plant's abatement project for CAP Minería.
Construction management and assembly to expand the storage capacity of the plant with 3 new tanks.
The project involved the construction of a new 10,000 m3 diesel storage tank.
The project consisted in the design of the new PANNA 4 ammonium nitrate plant, which expanded the Prillex America complex.
A "Grass Root" project was developed in a plant producing 120,000 tons per year of adhesive resins for wood panels.